Spalled columns. Corroded rebar. Structural cracks. Repair it right — once — and protect it for 20+ years.
A cement slap over a rusty rebar doesn't fix anything. Within 2 years: the patch falls off, the rust has spread further along the bar, and you have a bigger repair. The cost of doing it wrong is always greater than doing it right the first time.
Every step exists for a reason. Skip rebar treatment and the corrosion spreads under the patch. Skip bonding agent and the patch falls off. The system only works as a system.
| Method | FASTFIX System | Cement Patch | Epoxy Filler |
|---|---|---|---|
| Rebar treatment included | ✓ Yes | ✗ No | ✗ No |
| Bonding agent | ✓ SBR-50 | ✗ None | Partial |
| Structural strength | ✓ Matches concrete | Weak (no polymer) | ✓ Yes |
| Patch life | 15–20 years | 2–3 years | 10–15 years |
| Stops re-corrosion | ✓ Yes (CP200) | ✗ No | ✗ No |
| Cost per m² | ₹800–1,500 | ₹200–400 | ₹1,500–2,500 |
Critical: Apply only on bonding agent (SBR-50) while still tacky. Maximum 30mm per layer — deeper repairs require multiple layers with 24 hrs between. Do not add water beyond specified ratio.
₹990–1,350/m² materials. Labour adds 30–50%.
Compare to column demolition and reconstruction: ₹15,000–25,000/m². Repair typically saves 60–70% vs replacement when done correctly.
Sound entire surface — identify all delaminated zones. Break out all compromised concrete to solid substrate, going 25mm behind rebar. Expose all rusted steel.
⏱ Scope-dependent · Don't leave any loose concrete
Wire brush all exposed rebar to bright metal (St 3). Apply RR100 rust remover — leave 4 hours. Apply CP200 corrosion inhibitor coat. Allow 12 hours before mortar.
⏱ 2–3 hrs application · 12 hrs cure
Wet substrate. Apply SBR-50 bonding agent by brush to concrete and treated rebar. Do not allow to dry fully before applying mortar — must be tacky.
⏱ 1 hr · Apply mortar while tacky
Pack mortar in layers max 30mm. Compact each layer thoroughly — no voids. Multiple layers for deep repairs — allow 24 hrs between. Build to original profile.
⏱ 24 hrs per 30mm layer · Cure 7 days total
Apply COOLCOAT or AC200 over entire repaired area plus 200mm beyond. Seals surface against future water and CO2 ingress. Repair complete.
Total: 9–12 days for structural repair
Cosmetic cracks are surface-only, hairline (less than 0.2mm), and don't pass through the element. Structural cracks are wider, through-going, and often diagonal (shear). If a crack is in a beam, column, or slab and you're unsure — get a structural engineer to assess before repair. Wrong repair on a structural crack can be dangerous.
Yes — for structural cracks where load transfer is needed, epoxy injection (HARDPOXY INJ200) restores monolithic concrete. Use repair mortar (RM40) for volume replacements (spalling). Use epoxy injection for hairline to 10mm cracks where structural continuity is the goal.
Assessment is the first step — not assumption. A structural engineer can determine residual life. In most cases, buildings with rebar corrosion damage can be repaired and protected for 20+ more years at 30–50% the cost of demolition and reconstruction. Repair is almost always worth assessing first.
Three layers of protection: (1) CP200 on the rebar creates a passive protective coating on the steel. (2) RM40 repair mortar is polymer-modified — lower permeability than original concrete. (3) HARDSEAL AC200 anti-carbonation topcoat blocks CO2 from reaching concrete. All three together stop re-corrosion for 15–20 years.